County GovernmentTop story
San Joaquin County supervisors extend the data center moratorium by 10 months and 15 days
The extension came with a few numbers worth knowing
- 45 days
- length of the board's first moratorium, imposed Oct. 6
- Four-fifths
- of the board it takes to act on the extension
- 0
- data center applications pending in unincorporated areas
Source: Stocktonia
If you've wondered whether a data center could pop up in unincorporated San Joaquin County, the answer is not for now. The Board of Supervisors on Tuesday extended its moratorium on data center development for another 10 months and 15 days. Staff will review environmental and economic impacts and take community input.
“We owe our residents answers before allowing development that could have negative consequences for our environment and economy.”
Board Chair Sonny Dhaliwal
Supervisors Steve Ding and Paul Canepa were absent when the board first took it up, so a formal decision waited until Nov. 17, Stocktonia reported. The deeper study will also look at whether a fire in massive battery storage units could overwhelm firefighters in small rural fire districts.
- Full staff report: not expected until next June
- Issues on the table: electricity demand, water use, noise
- Stockton: council cut data centers from its three-year economic plan
- Stockton: public listening sessions are underway around the city
The county's data center pause has been extended by 10 months and 15 days
- Oct. 6Supervisors impose a 45-day moratorium on data centers.
- Nov. 17Board extends the moratorium for 10 months and 15 days.
- JuneStaff's full report on data centers is expected.
Sources: Lodinews.com, Stocktonia